City Of Houston · Houston, TX · Completed 2024. Treatment capacity expanded while the plant kept meeting demand every day.
ClientCity Of Houston
MarketMunicipal & State
LocationHouston, TX
Contract Value$264.0M
Duration2020 – 2024 · 58 Months
StatusComplete
The Program
The City Still Needed Its Water.
Plant expansions are tie-in problems wearing a construction costume. The existing facility has to keep producing to spec while new trains are built alongside it and cut in one at a time.
Each tie-in was planned against demand rather than against the contractor's preferred sequence, and no cut-in was released until the redundancy behind it had been demonstrated.
On The Ground
6 PhotographsWide shot
Detail
Detail
On site
On site
On site
Selected Work
More Municipal & State Programs
Project photograph
Municipal & StateLaredo, TXPublic Safety Complex
City Of LaredoView Project
Project photograph
Municipal & StateHouston, TXPrecinct Drainage Improvements
Harris County - AGCMView Project
Project photograph
AviationHouston, TXTerminal C North Concourse Modernization
Houston Airport SystemView Project