Project

Terminal C North Concourse Modernization

Houston Airport System · Houston, TX · Completed 2025. Delivered in eleven phases without closing a single active gate.

ClientHouston Airport System
MarketAviation
LocationHouston, TX
Contract Value$312.0M
Duration2021 – 2025 · 47 Months
StatusComplete
The Program

Eleven Phases, Not One Gate Closed.

Terminal C North handles roughly 30,000 passengers a day. The concourse could not be taken offline, the apron could not be closed, and the airline's schedule was fixed a year in advance. Everything else had to bend around that.

PMG sequenced the work into eleven phases, each sized to a single overnight window between the last arrival and the first departure. We held daily coordination with airline operations, TSA and airport security, and rebuilt the schedule weekly against actual gate availability rather than the plan.

The concourse opened on the contract date. No gate lost a single scheduled departure to construction across four years.

On The Ground

6 Photographs
Wide shot
Detail
Detail
On site
On site
On site
Selected Work

More Aviation Programs

View All Projects →
Project photograph
AviationHouston, TX

Hobby Airport Ramp Rehabilitation

Houston Airport SystemView Project
Project photograph
AviationHouston, TX

Terminal B Baggage Handling Upgrade

Houston Airport SystemView Project
Project photograph
AviationLaredo, TX

Laredo International Terminal Expansion

City Of LaredoView Project